Kanban Board - Notes

In the Kanban board, when I'm clicking on "Add Notes", it doesn't select the Task/Project automatically unlike when clicking on "Add Task", it automatically select project in which the "Add task" button is clicked. 

jainnilesh_0-1732580237705.png

jainnilesh_1-1732580289791.png

 

How can it be resolved? Currently scrolling through Task under "Note form" takes a long time. 

Thanks

 

Solved Solved
0 3 280
1 ACCEPTED SOLUTION

Please try below for having notes option both in Projects and Tasks table.

Please have two reference columns [Task] referencing Tasks and [Project] referencing Projects table.

Suvrutt_Gurjar_0-1732675344556.png

The configuration of the [Task] column to be as follows

Suvrutt_Gurjar_1-1732675464627.png

The configuration of the [Project] column should be as follows

Suvrutt_Gurjar_2-1732675634692.png

 

The action "Add Project Note" in the Projects table should be as follows

Suvrutt_Gurjar_4-1732675837677.png

 

The action "Add Task Note" in the Tasks table should be as follows

Suvrutt_Gurjar_5-1732675927845.png

 

 

 

 

 

View solution in original post

3 REPLIES 3